Building the evidence for the future
Preparing a Local Planning Scheme is a long-term process that begins well before a draft scheme is prepared.
The Preliminary Work stage builds the evidence needed to prepare the draft Local Planning Scheme. While not required under planning legislation, the City has chosen to engage with the community early so local knowledge, technical investigations and feedback can help inform the draft before it enters the formal statutory process.
The key components of the Preliminary Work are outlined below, followed by a timeline of the investigations, engagement activities and milestones completed to date.
Preliminary Work Timeline
-
Timeline item 1 - complete
Report of Review - Preliminary engagement
26 October - 9 November 2021
Preliminary engagement with community and key stakeholders
-
Timeline item 2 - complete
Prepare Report of Review
November 2021
Preparation of draft Report of Review
-
Timeline item 3 - complete
Ordinary Meeting of Council
14 December 2021
Council approve Report of Review recommendations
-
Timeline item 4 - complete
Refer Report of Review to WAPC
20 December 2021
Refer Report of Review to WAPC for determination
-
Timeline item 5 - complete
WAPC determination on Report of Review
27 May 2022
WAPC determined to support the recommendations in the Report of Review
-
Timeline item 6 - complete
Community consultation
20 March 2023 to 8 May 2023
Community input to help shape the scope of the review
-
Timeline item 7 - complete
Elected Members Engagement Session
July 2023
Project scope finalisation and engagement findings
-
Timeline item 8 - complete
Elected Members Engagement Session
June 2024
Residential density and scheme zoning workshop
-
Timeline item 9 - complete
Community consultation
17 July -18 September 2024
Community invited to view the proposed amendments on zoning and density changes
-
Timeline item 10 - complete
Ordinary Meeting of Council
18 February 2025
Council acknowledge community petition
-
Timeline item 11 - complete
Ordinary Meeting of Council
9 December 2025
Council endorse the Staging and Implementation Plan
-
Timeline item 12 - complete
Technical studies
October 2025 – February 2026
Further technical studies undertaken to inform proposed scheme changes
-
Timeline item 13 - active
Elected Members Engagement
February - September 2026
Workshop series
-
Timeline item 14 - complete
Ordinary Meeting of Council
16 June 2026
Revised density approach presented to Council ahead of Phase 6 community consultation
-
Timeline item 15 - active
Community consultation
20 July - 31 August 2026
Revised approach presented to community for feedback.
-
Timeline item 16 - incomplete
Elected Members Engagement Session
20 October 2026
Draft report presented to Elected Members.
-
Timeline item 17 - incomplete
Ordinary Meeting of Council
Q4 2026 / Q1 2027
Council to consider endorsement of final draft for WAPC consideration.
-
Timeline item 18 - incomplete
Draft Scheme submitted to WAPC
Q4 2026 / Q1 2027
Submit for WAPC approval with recommendation and request to advertise (may take multiple rounds)
-
Timeline item 19 - incomplete
Minister approves Scheme for advertising
TBA 2027
Minister either approves scheme amendment for advertising or requires the scheme to be modified
-
Timeline item 20 - incomplete
Statutory process
Once the draft Local Planning Scheme has been prepared, the project will move into the Statutory Process. Explore the Stage 2 page to learn more about what happens next.